Kitchen Floor


HOME


In the early part of 2024 we noticed the kitchen floor by the door to the side of the house had started to swell. Moisture had somehow penetrated from outside and gotten under the laminate. So, the decision was made to bite the bullet and have the entire kitchen floor replaced. We didn't want to do laminate again because if it got wet we would have to deal with this all over, so we looked only at tile. It took weeks before we settled on something we liked. Then, of course, the tile we wanted was backordered so we had to wait an additional month before we could pick it up. Despite, the delay we ordered the tile and had our contractor set a date to remove the old laminate, level the kitchen floor, install an underlayment, and then finally install the tile. When the job was about 85% done we discovered there wasn't going to be enough tile. Luckily, it didn't take as long to reorder some more so the delay was only a couple of days. It was during this down time we noticed some of the 12" x 24" tile we liked didn't lie flat. There was a bow in the middle of some of the pieces causing uneven high spots. We thought about it long and hard and decided to stop the job and reconsider whether or not to proceed with the tile we bought. We were very fortunate that our contractor was sympathetic to our concerns and he said if it were him he'd stop and get something else. This meant we would have to go back to the drawing board and find new tile or some other alternative. During this time we discovered vinyl laminate that had an almost hardwood look and feel but was, more importantly, waterproof. Installation would also be much easier. The problem was the newly installed tile would have to be completely removed before the new laminate could be put down. We set a date with our contractor in the early part of September when he would remove the old/new tile and install the vinyl. From beginning to end, the total time was longer than we imagined, but we're completely happy with the results.


February 13, 2024

old floor

Old floor.

old floor 2

Old floor.


swelling

Water penetrated laminate.

swelling

Swelling.

removal

Removal of bad pieces.


June 17, 2024

cabinets

Covering cabinets.

appliances

Moving appliances.

underlayment

Installing underlayment.


underlayment

Underlayment.

level

Self-leveling compound.

level

Almost done.


June 18, 2024

laying it out

Laying it out.

other side

Other side.


June 19, 2024

starting

This is what it will look like.

other side

Other side.


June 20, 2024

still going

Adding some more tile.

other side

Getting closer.

laundry closet

Laundry closet.


June 21, 2024

done

This is finished.

done too

This side is done too.

almost there

This is when we ran out of tile.


so close

So close.

looks pretty good

From here it looks good.

samples

Looking at samples (7/8/24).


September 3, 2024

removal begins

Starting to remove tile.

not easy

Not an easy job.

dishwasher

Getting there.


really dusty

Lots of dust.

plywood

Down to the plywood.

took all day

They removed it all in one day.


After the old/new tile was completely removed, our contractor said the new floor would go down in a day. The issue was that when the tile was installed, all our baseboards were cut to accommodate the thickness of the tile. Since the laminate is much thinner he had to go out and find new baseboards not only for the walls but the cabinets as well. Also, to make sure water doesn't penetrate by the door again, new weather stripping was installed along with a new door sweep. All told, this work only took two days to complete.


September 5, 2024

floor is done

Floor is done.

looks nice

Looks very nice.


all done

Finished.

new weather stripping

New weather stripping installed.